We’re upgrading the M40/M42 Interchange to reduce congestion and improve journey times. We’ll shortly start some overnight survey work to gather information to inform the final design of the scheme.
How will the survey work affect road users?
We’ll put the following closures in place overnight from 9pm to 6am:
M42 Northbound to M42 Northbound Link at J3a – January 5, 6, 7, 8 & 11
M42 Southbound to M42 Southbound Link at J3a – January 12, 13, 14,15 & 18
M40 Northbound to M42 Northbound Link at J3a – February 15, 16, 17, 18 &19
M42 Southbound to M40 Southbound Link at J3a – February 22, 23, 24, 25 & 26
In addition, we’ll continue our main carriageway surveys in the following locations:
· M42 J3a – M40 J16 from mid-January for 6 weeks
· M42 J3a – 4 from end-February for 6 weeks